Standardized Work Introduction-04
4.0 Takt Time Calculation 节拍时间计算
Takt Time is the rate of production, in seconds per piece,needed to meet customer demand.
Takt =Seconds per week worked / Customer demand per week
节拍时间是满足客户需求所需的生产率(单位=秒)
节拍=每周工作秒数/客户每周需求数量
· Takt Time iscalculated from: 节拍时间计算依据
1. Available seconds per day toproduce it 每天可用来生产的时间秒数
2. Customer demand per day 客户每天需求数量
4.1 Determining the Normal Factory Work Hours 正常工作时间
Determine how many shifts the production area is runningper day (under normal working conditions). Subtract any normally plannedcontractual time, such as breaks and lunches, when the area would not berunning. This is the “Available Time.” Convert into seconds.
确定生产区域每天运行多少个班次(正常工作条件下),减去正常的作息时间,例如休息和午饭.这是“可用时间”并转换为秒
4.2 Takt Time Calculation 节拍时间计算
Now figure the customer demand for this area. Once you know the customer demand, you areready to calculate Takt! Divide the Availabletime in Sec by the Customer demand
现在计算该区域的客户需求。当你知道了客户需求,你已经准备计算节拍!
用可用时间除以客户需求.
4.3 Takt Time calculation: example 节拍时间计算
Working 1 shift per day 每天运行1个班/8小时
480 min shift – 54min breaks & lunch(休息&吃饭) = 426 min availabletime (可用时间)
426 min per day X 60sec/ min = 25,560 sec /day (每天可用时间/秒)
Weekly demand is10,000 pcs / wk 每周客户需求数量:10,000
Daily demand is 10000pcs/wk ÷ 5 days/wk = 2,000 pcs /day每天2,000个
Takt = 25.560 sec/pc ÷ 2000 pcs/day = 13 sec/pc
节拍=每天可用时间/每天客户需求数量=13秒/个